Project Comments |
 |
Increased capacity of available electricity supply to store to cater for new refrigeration plant and equipment and future loads by installing replacement 2000kVA transformer. |
 |
Replaced the incoming mains distribution equipment to provide seperate essential and non-essential services facilities. |
 |
Installation of new distribution cables and boards for additional refrigeration plant. |
 |
Rationalisation of the existing distribution to keep essential load demand within the capacity of the existing standby generator. |
 |
All work was carried out during Sunday night / Monday morning to prevent disruption to store opening times. |