JSH Consulting.co.uk

   
Parallel UPS & Bypass arrangement
Parallel UPS & Batteries etc
 
Client : 

Sheffield Hallam University

Site :

Collegiate Crescent Campus

Project Name :

New Server Silo

JSH Involvement : 

Electrical and Mechanical Services Design

Scheme Outline :

Conversion of existing rooms into fully air conditioned space for housing server equipment. Backup power from parallel operating UPS's.

Main Contractor :

Longcross

Sub Contractor(s) :

None

Scheme Value : £135,000

 

Project Comments

Installation of parallel 60kVA UPS systems to give system power resillience.

Automated controlled shutdown of the universities server equipment.

Rationalisation of the mains supplies to the building and to its distribution systems to allow the introduction of the new electrical loadings.

Installation of dual distribution and final circuit arrangements to minimise the possible risk of supply failure due to individual components.

Installation of UPS bypass facilities and connection for temporary generation plant in the event of long term mains failures.

 

 

   
© 2010 JSH Consulting Ltd