| Client : |
Derbyshire County Primary Care Trust |
| Property / Site : |
Walton Hospital, Chesterfield. |
| Project
Name : |
Boiler house decentralisation. |
| JSH
Involvement : |
full design and project management. |
| Scheme
Outline : |
New main incoming services, phase decommissioning of central plant and installation of plant room equipment. |
| Main
Contractor : |
Murphy Pipelines Ltd and Hallamshire Heating Co. Ltd. |
| Sub
Contractor(s) : |
Electrical, building, controls and thermal insulation. |
| Scheme
Value (M&E) : |
£900,000 |
Project Comments |
 |
Detailed assessment of current and future loads, design and project management of enabling works package compising site wide distributed power, gas, mains and fire fighting water. |
 |
Design, specification and project management of 7 no. remote plant rooms. |
 |
Phased decommissioning of the existing central boiler house and tank cold water system. |
 |
Post completion Note: Annual gas consumption reduction of 45%. |
| |
|
|
|
|